refit in January but building delays pushed everything back 6 months Annex build allows for two must haves ◦ Dedicated electric supply for garage/brewery (10mm2) ◦ Proper brewery floor drainage and epoxy floor coating Date Action March New walls April Concrete floor/drainage May New stud wall between garage/brewery June Hygienic wall cladding & epoxy floor coating July/August Reinstall of brew kit incl. electric, plumbing September Test Brew ? October – done!
remove chlorine/chloramine HLT - 100lt with 3kw heater and small recirc pump to keep even temperature Double layer camping mat insulation Mash Tun - 100lt, perforated false bottom Double layer camping mat insulation Boiler – Twin walled & insulated. 9kw heater but only use two of the elements Plate heat exchange to cool hot wort All control panels are DIY Just added extractor and electric bug zapper! 11